Monday, February 13, 2017

Couple More Tickboxes Checked Off

Openreach has completed a run of Fibre down the 404 and across traffic to near our exit from the 404 North.  This is the good news.  The bad news is that the task of running the fibre through our existing duct works requires a specialist contractor and to the best of our knowledge this has not yet been scheduled (our Openreach contact is on holiday).

As of today another contractor, working on behalf of Call Flow, is connecting power to the new cabinet that will house our high speed connection hardware.   We have asked Call Flow for an update on how long it will take to offer us service once the fibre is connected but our contact there is on holiday.

Finally, given all the holidays above, I reached out to Superfast Berkshire to see if they had any news. Guess what?  On holiday!  I kid you not.  Is there a special telecoms conference going on somewhere this week?

Hopefully the duct works overlay part of the project will be scheduled soon and will not encounter any issues.

This is where it would be nice if we could have to paths being pursued at one time. 